A Background
Paper
for the
Development of
A Plan for
the Future of the
by
the
1.Introduction1
4Habitat Potential and Estimated Potential Runs for Restored Migratory Fisheries9
5.State
Agencies’ Draft Plan for Fisheries Management for the
6.Legal Context12
7.Fisheries Management Opportunities and Options13

The Casco Bay Estuary Project (CBEP) is assisting
the
Fisheries management is one of the central issues
in planning for the
As part of the CBEP planning process, a Steering Committee
composed of representatives of federal, state and local government agencies,
conservation organizations and interests, and SAPPI Fine Paper, Inc., has
been working cooperatively to develop an information base and proposed
management options to discuss at public meetings.This
Background Paper presents an overview of the existing and potential resident
and migratory fishes of the
2.Existing
Fisheries
The existing fishery of the
(1) an intensively managed trout and salmon fishery located primarily in the restored Eel Weir Bypass, the natural river channel below Sebago Lake, and in the tailraces below the downstream dams;
(2) resident species, primarily bass, perch, and bullhead, found in the series of impoundments that characterize nearly 22 miles of the river[1] below the Eel Weir Bypass (from the upper end of the North Gorham impoundment to the Smelt Hill dam); and
(3) migratory species, principally eels, found in all the impoundments, and alewives, found seasonally in the river below the Cumberland Mills dam.
Recreational
Sport fisheries
are comprised primarily of:
·brown
trout
·smallmouth
bass
·largemouth
bass
·brown bullhead
·yellow
perch
Of
these the bass and brown trout are introduced species; a number of other
less important species have also been introduced.
Fish Stocking:MDIFW
stocking programs maintain recreational fisheries for trout and landlocked
salmon.These fisheries occur in the
tailrace and bypass reaches associated with Eel Weir Dam, North Gorham
Dam, Dundee Dam, Mallison Dam.The
Eel Weir bypass (approximately 1.25 miles in length), is located immediately
below Sebago Lake, and is intensively managed for brook trout (up to 2,500
fish annually), although, landlocked salmon, and to a lesser extent brown
trout are also stocked.The other
three bypass reaches that are the focus of MDIFW stocking programs are
managed primarily for brown trout and are stocked annually at much lower
levels, typically 250 trout per reach.Some
tributaries to the
Migratory Species:Two
species of migratory fish presently utilize the
·American
eels, which spawn in the ocean and migrate into the river to mature
to adulthood.Because young eels
(elvers) can wriggle over or around dams, American eels are able to migrate
up the river, ascending the dams to reach all the way to
·Alewives,
which migrate upriverto spawning
grounds in lakes and ponds, and return to sea to mature into adults.This
species had access to the lower Presumpscot and
The relative abundance
and condition of
Assessments of Abundance and Condition:Studies documenting the abundance or condition of the fisheries in the Presumpscot River have been developed as part of the relicensing efforts for hydropower projects, to document the success of fishery restoration efforts in the Eel Weir Bypass after flows were restored, as part of the State’s dioxin sampling program, and to characterize the potential for Environmental Restoration at the Smelt Hill Dam and in the lower Presumpscot.
Based on the above
assessments and local knowledge offered by regional fisheries biologist
·The
Eel Weir Bypass supports a robust put-and-take trout and salmon fishery,
as well as an assemblage of other fishes including lake trout (drop-downs
from
·The
·The
o·The
Gambo impoundment supports a more limited fishery for smallmouth bass and
yellow perch.
·The three downstream impoundments (Little Falls, Mallison, and Saccarappa) provide lower quality habitat for many species of fish because, as outlined above, they are neither truly riverine nor lake like.
· Below the Saccarappa dam the same assemblage of fish is likely to exist as above Saccarappa, except that below Cumberland Mills, some migratory fish (alewives, blueback herring, shad, and striped bass) may be present as a result of the removal of the gates at the Smelt Hill dam.There is no information on the abundance or condition of the fish in this portion of the river.
·Eels are common in all of the impoundments.
Fisheries
Habitat Conditions in the
Assessments of
Fish Habitat on the
Existing fisheries
habitat in the
Habitat Impacts from Dams:Presently,
there are 9 dams on the
Dams on the
|
Dam
|
Miles
from
|
Use
|
Owner
|
Comment
|
|
Eel
Weir
|
|
hydropower
project
|
SAPPI
|
outlet
of
|
|
|
|
hydropower
project
|
FPL,
LLC
|
|
|
|
|
hydropower
project
|
SAPPI
|
|
|
Gambo
|
|
hydropower
project
|
SAPPI
|
|
|
Little
Falls
|
|
hydropower
project
|
SAPPI
|
|
|
|
|
hydropower
project
|
SAPPI
|
|
|
Saccarappa
|
|
hydropower
project
|
SAPPI
|
|
|
|
|
process
water/
fire protection |
SAPPI
|
|
|
Smelt
Hill
|
|
Inoperable
|
CMP/DMR
|
head-of-tide;
to be removed
|
These dams have two effects by limiting access to habitat:
·First,
the dams blockthe upstream migration
of sea-run fish that return to freshwaters to spawn (including Atlantic
salmon, shad, blueback herring, and alewives).Young
American eels also migrate into freshwaters to mature prior to returning
to the sea to spawn.The American
eels are able to ascend over and around the dams, and are found in all
of the impoundments; however, the Department of Marine Resources believes
the number that are successful in migrating up the Presumpscot are fewer
than would occur naturally.
·Secondly,
the dams have isolated sections of the river (fragmenting the river habitat)
restricting the free movement of fish and reducing the ability of both
resident and migratory fishes to reach spawning areas in the river and
tributaries, and cold water refuges during hot weather.
Dams have also altered the ecology of the river as follows:
·The
dams created a series of impoundments that replaced the natural pools,
riffles, runs, and falls originally present in the river.Impoundments
now occupy approximately 22 of the 26 miles from head of tide to
![]()

|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note:Elevations
at the top of each dam are shown next to the names of the dams.
Sources:
Federal Emergency Management Agency: Flood Insurance Study.
Prepared
by:
·The impoundments are unable to function like a natural river, lake or pond, and as a result, the abundance and diversity of the benthic (bottom dwelling) organisms are diminished compared to a river, lake or pond.The Maine DEP has found:
“In effect, the ponded area assumes some of the characteristics of a lake, but typically the ponded water volume has a much shorter retention time, as compared to a natural lake.Thus the riverine biological community is subjected to quasi-lake conditions for which they are not adapted.Lake dwelling organisms generally, also find run-of river impoundment conditions unfavorable.The short retention time precludes the possibility of development of a planktonic community, the typical food base of lakes.High flow volumes in spring and fall, experienced by the river are also reflected in riverine impoundments, frequently causing scouring of accumulated organic matter on the substrate, and partially restoring the riverine, mineral-based substrate.This constitutes a periodic disturbance of benthic habitat for typical lake dwelling organisms, resulting in lower production.Biological assessment of impounded benthic communities reveals that the detrimental effects of these unnatural conditions usually results in severe loss of both community structure and function.” (Maine DEP, Biomonitoring Retrospective, 1999).
|
Characteristic/ Aspect |
Eel Weir Bypass |
Impoundment |
to |
to Gambo Dam |
to Little
Falls Dam |
to |
|
to |
|
|
Reach Length (miles):(see
column headings)
Impoundment Area (acres) Impoundment Depths (ft) Length impounded (miles) ~Length “free-lowing”(miles)1 Natural Riverbed Profile Elevation Drop in (ft)
2 Average
drop (ft/mi) |
1.25 none none none 1.25 34 27. |
1.1 98 max 23 1.1 none 28 26 |
1.77 197 10 – 44 1.77 none 56 32 |
3.24 151 max
15 3.07 875 feet 22 7 |
1.71 29 12 - 15 1.65 300 feet 22 13 |
0.55 8 max 9 0.50 300 feet 16 29 |
5.53 87 max 28 5.52 300 feet 40 7 |
1.23 31 max 20 1.14 475 feet 20 16 |
6.85 107 26 at Smelt
Hill Dam ~6.53 ~1,700 feet 20 3 |
|
1Free
flowing means not backwatered by the downstream impoundment; these lengths
are, excepting the Eel Weir Bypass and the river immediately below the
Cumberland Mills dam, areas of the river below dams where flows have been
bypassed through diversions to downstream powerhouses, and hence they have
much reduced flows, and at times,no
flows.
2Drop
in riverbed elevation, in feet, from base of upper dam to base of lower
dam. |
|||||||||
Substrate
(River Bottom) Conditions Affecting Fish Habitat: Substrate (the characteristics
of the river bottom) is an important factor defining habitat conditions
for fish.Several species of fish
that presently or potentially could inhabit the
Four studies have documented substrate conditions from the Smelt Hill Dam to the Dundee Impoundment.In brief, the findings of these studies, which differed significantly in the methods they used, show that fine sediments predominate in near shore areas and are progressively more common downstream. Mid channel areas (in the vicinity of the original river channel) in the upper part of the river have coarser substrates, including gravel and cobble sized materials.
Water Quality as an
Influence on Fish Habitat: Water
temperature and oxygen conditions affect the suitability of waters for
fish, with certain species such as trout and salmon requiring colder and
more oxygenated water than bass and other pan fish. Like
many other small coastal rivers in southern Maine, during the summer the
Presumpscot River water temperatures are limiting for native trout and
salmon species outside of any coldwater refuges that may exist near springs.This
is true of both the impounded and unimpounded reaches, including the Eel
Weir Bypass. In the summer, native brook trout move to colder water near
springs or in the tributaries where waters are naturally cooler due to
shade and a higher groundwater component to the flows (base flows).Waters
that support trout and salmon during the fall, winter and spring include
the Eel Weir Bypass, the
The source water for
the
Below Cumberland Mills the water quality of the river once was severely impacted by industrial and municipal discharges, but has improved since treatment plants were constructed in 1970’s, and recently (since 1999), even more significant improvements have resulted due to the cessation of the pulping operation at the SAPPI (formerly S.D. Warren) mill in Westbrook.Although DEP has not monitored the river since the shutdown of the pulping operation, it is apparent that water quality has improved and there are plans to begin monitoring after the Smelt Hill dam is removed.
3.Historical
Conditions for Fisheries in the
Early
historical accounts document a long history of controversies related to
blockage of fish migrations by dams on the river.The
first dam was constructed at the head of tide,
The controversy continued
after Chief Polin’s death, as blockage of the river not only affected the
Rockomeecook Tribe, it also eliminated a source of food for the early settlers
and impacted Cod fishermen.Hence,
on October 30, 1781 the selectmen of the towns of Gorham, and agents from
the towns of Windham, Standish and Bridgton (which includes the Crooked
River flowing into Sebago Lake), petitioned the Governor and Legislature
of the Commonwealth of Massachusetts to “appoint a Committee that shall
cause goodand sufficient fish courses to be made through the several dams
on the river” to restore the fisheries to the river.They
stated that the
Other historical
accounts related to the original fisheries of the
·In
the History of Gorham by Hugh McLellan, 1903, there is this account:
“Parson Smith in his journal says,
·Charles Fobes, in “The Story of the Presumpscot” included in the Collections and Proceedings of the Maine Historical Society, 1894, has this account:“In October 1793 the proprietors of the dam at Great Falls [near the present site of the North Gorham dam] were found guilty of not keeping open a good and sufficient sluiceway for the passage of salmon, shad, and alewives as required by law and were subjected to a fine of six pounds per day for every day the way was closed.”[parentheses added]
·Charles
Atkins, in his report “The River Fisheries of Maine” included in a report
from the United States Commission of Fish and Fisheries to the 47th
Congress in 1887, says of the
· Charles Atkins, in the Fish Commissioners Report of 1867, states: “In this vast reservoir [referring to Sebago Lake], the turbid water of the tributary streams deposits its sediment, and issues thence [the Presumpscot River] as a river of uncommon transparency, a character which is maintained for a long distance from the lake.” [parentheses added]
4.Habitat
Suitability and Potential Runs of Migratory Fisheries
Habitat Suitability
for Migratory Fishes from Smelt Hill Dam to
Habitat Suitability for Migratory Fishes above Cumberland Mills Dam:If access is provided to upstream habitats above the Cumberland Mills dam, through fish passage and/or dam removals, the DMR and the Atlantic Salmon Commission expect the Presumpscot River above Cumberland Mills and its tributaries will provide habitat (for migration, spawning, or growth) for American eel, American shad, alewives, blueback herring, Atlantic salmon, sea-run brook trout, sea-run brown trout, and possibly striped bass.
Estimated Maximum
Potential Migratory Fish Runs – Shad, Blueback Herring, and Alewives:The
Department of Marine Resources has developed “order of magnitude” spreadsheet
models for estimating the size of American shad, blueback herring, and
alewife runs that could be supported by river and lake impoundment habitats
if suitable access is provided for these fish species.The
table which follows shows the potential fish populations that could be
sustained by habitat in the various reaches of the river up to the North
Gorham dam, including three major tributaries, the Piscataqua River, the
Little River and the Pleasant River (for shad and blueback herring), as
well as Highland Lake (for alewives only) if there were no dams on the
river or fish passage were 100% efficient.This
represent the maximum expected population that could be sustained assuming
100% of the river habitat is suitable for these species, and given unimpeded
access to the various sections of the river.
by Reach of the
|
Location
|
|
(98.8/acre) |
(46 –
182/acre) |
|
|
|
|
Smelt
Hill to
|
107
|
10,500
|
|
64,000
|
|
|
|
|
629
|
|
|
|
147,700
|
|
|
|
23
|
2,300
|
|
14,000
|
|
|
|
Subtotal
below
|
|
12,800
|
|
78,000
|
147,7004
|
238,500
|
|
|
31
|
3,100
|
|
18,800
|
|
|
|
Saccarappa
to
|
100
|
9,900
|
|
60,200
|
|
|
|
Little
River
|
39
|
3,800
|
|
23,300
|
|
|
|
Mallison
Falls to Little Falls
|
11
|
1,100
|
|
6,600
|
|
|
|
Little
Falls to Gambo
|
32
|
3,100
|
|
19,000
|
|
|
|
Gambo
to
|
120
|
11,900
|
|
72,200
|
|
|
|
Pleasant
River
|
83
|
8,200
|
|
50,100
|
|
|
|
|
13
|
1,000
|
|
8,000
|
|
|
|
|
191
|
19,000
|
|
114,000
|
|
|
|
Subtotal
above
|
|
61,100
|
|
372,200
|
|
433,300
|
|
Grand
total
|
|
73,900
|
|
450,200
|
147,700
|
671,800
|
|
1Maine
currently has no rivers with extensive runs of American shad, and historical
information on run sizes is lacking, therefore run sizes must be estimated
from information on restored runs in other rivers.In
the past, DMR has used 111 shad/acre, based on the run of American shad
in the
2
Based on estimates from the 3Based
on data from commercial alewife harvests on six 4If
alewives are able to reach Knight’s Pond and |
||||||
Estimated Maximum
Potential Atlantic Salmon Run:The
Maine Atlantic Salmon Commission (MASC) has developed estimates ofthe
size of a potential Atlantic salmon spawning run assuming passage is provided
at all dams, or assuming three dams are removed (Saccarappa, Mallison Falls,
and Little Falls) and passage is provided at the remaining dams.Estimates
were also developed by the Berger Group, Inc., a consulting firm hired
by the Federal Energy Regulatory Commission.These
are shown below.The available habitat,
if all dams remain, is located primarily in the tributaries to the river,
as the only mainstem area with suitable habitat with all dams remaining
is in the Eel Weir Bypass.Tributaries
with suitable habitat include the
Estimated Atlantic Salmon Spawning Runs on the
|
Scenario
|
|
|
||
|
|
|
|
|
|
|
Passage
at all dams |
N/A |
5,283 |
N/A |
124 - 620 |
|
Removal
of Saccarappa,
|
2,276 |
7,485 |
34 - 102 |
206 – 1,030 |
|
1Berger
estimates are based on habitat available in the mainstem only (which is
very limited), and assume a survival and return rate of 0.5% to 1.5%.
2MASC
estimates are based on habitat available in the tributaries, and assume
only the Eel Weir bypass has suitable habitat in the mainstem; and assumes
a 1%to 5% survival and return
rate. |
||||
5.State
Agencies’ Draft Plan for Fisheries Management
for
the
A Draft Fishery Management Plan for the Presumpscot
River Drainage was prepared by the
The management plan goals contemplate restoration of migratory fish runs in phases, allowing the fisheries agencies to assess potential interactions between resident and migratory species and changes in fishing opportunities.During Phase 1, migratory fish would be restored as far as Gambo dam.If the three fisheries agencies agree, restoration would continue up the river in Phase 2.
6.Legal Context
Related Laws and Regulations:A
number of state and federal laws and regulations have a bearing on the
future of the
Status of Legal Proceedings:With the exception of Cumberland Mills Dam, all the dams are components of hydroelectric power plants, and are licensed by the Federal Energy Regulatory Commission (FERC).
Smelt Hill Dam.Removal of the dam is expected to begin in July and be completed in November of 2002.
Saccarappa
Project to
Eel
Weir Project FERC License Application.SAPPI
is in the process of relicensing the Eel Weir Project, including the Eel
Weir Bypass section of the river.
7.Fisheries
Management Opportunities and Options
With the removal
of the Smelt Hill dam, migratory fish will have unimpeded access to the
lower seven miles of the
The
goal of the Steering Committee preparing the Plan for the
Options:There
are several possible courses of action to enhance fish resources
in the
The options outlined below are included as a starting
point for discussions on how the river could be managed to enhance or restore
fisheries. Only option 3b would fully achieve the current management goals
established by State and Federal agencies for fisheries’ restoration on
the Presumpscot.
Option 1 – No further action is taken beyond removing
the Smelt Hill Dam
Description:Under
this option, sea run fish would be restored to approximately 7 miles of
the lower river below the Cumberland Mills dam after the Smelt Hill dam
is removed (expected in the summer/fall of 2002).In
addition, this would provide access to the
Costs:Estimated costs of $1.1 million are to be paid by State and Federal funds and private donations.
Effects
on Migratory Fish:Runs of a number
of migratory fishes are expected to develop. In addition to American shad,
alewives, blueback herring, American eels and striped bass, additional
runs are possible for a number of species, includingsea-run
brook troutsea-run brown trout, Atlantic
sturgeon,rainbow smelt and tomcod.The
estimates below are a compilation of a number of estimates.The
Maine Department of Marine Resources has estimated runs of adult shad,
alewife and blueback herring spawners resulting from Smelt Hill dam removal.The
Maine Atlantic Salmon Commission has estimated potential Atlantic salmon
runs on the Presumpscot.The Federal
Energy Regulatory Commission contracted with Louis Berger Group, Inc. to
evaluate the impacts of removing one or more of the following dams: Saccarappa,
Effects
on Resident Fish: Above
Cumberland Mills dam, in the impounded reaches (nearly 15 miles), the fisheries
of the river would continue to be composed primarily of bass, perch, bullheads,
and sunfish, and the productivity of these fish would continue to be compromised
as a result of the nature of shallow river impoundments.A
fall to spring fishery of trout and landlocked salmon in the
Consistency with State and Federal Management Goals:This option does not meet the goals and objectives of the State fisheries management agencies (DMR, IF&W, and MASC) as expressed in their December 2001 “Draft Fishery Management Plan for the Presumpscot River Drainage.” (see Section 5 and Appendix C of this report).It also does not address the US Fish and Wildlife Services goals, as reflected in their filings to FERC prescribing fish passage on the dams below the Eel Weir Dam, provided passage is achieved at the Cumberland Mills Dam, and sufficient numbers of migratory fish return to the river.
Estimated Migratory Fish Runs with Smelt Hill Dam Removed
|
Migratory
Species
|
Estimated
# Returning Adult Fish
|
|
American
shad(including
a run on the |
6,000
– 23,7001 |
|
alewives(migrating
through to
possibly |
150,000
– 200,000
|
|
blueback
herring
(including a run on the
|
78,0002
|
|
Atlantic
salmon
|
23
– 115 (MASC) 3
|
|
American
eel
striped bass(as far as Cumberland Mills) |
increased
numbers
|
|
1Based
on runs documented 1983- 2000 on the
2 Estimate
by Maine DMR based on estimates of 600 river herring/acre on the 3
Assumes Atlantic salmon will utilize habitat in the |
|
Option 2 – Smelt Hill Dam is removed and the resident
fisheries are enhanced
Description:In
addition to the fisheries resulting from the removal of the Smelt Hill
dam under Option 1, above, enhanced management would result in increased
stocking of trout in the tailrace areas below
Costs:
The additional cost for increased trout stocking would be approximately
$3,000 and would be part of the Maine Department of Inland Fisheries and
Wildlife’s budget (estimated increases in stocking and costs provided by
Effects
on Migratory Fish:Same as Option
1: the lower river, below the
Effects on Resident Fish:Under this option the Eel Weir Bypass reach would continue to provide exceptional fishing as described in Option 1.Additional stocking of trout would result in an enhanced seasonal fishery for stocked trout.Since the existing habitat is sparse and fragmented, the trout fishery would continue to depend on stocking and would not develop into a robust self-sustaining population.Some of the methods for enhancing bass and pan fish, e.g., adding woody material, are only stable in areas where there is not significant flow, even during floods.Further, these methods can create boating hazards and add to the amount of debris carried down the river.No quantitative estimates are available for how much these actions would improve fish populations; however, the Maine DEP found that narrow riverine impoundments function neither as river or lake environments, and as a result the productivity of these systems is relatively low.Therefore, even if the cover present in the impoundments was enhanced by the activities outline above, there is a risk that the fisheries would be improved only marginally.
Consistency with State and Federal Management Goals:This option does not meet the goals and objectives of the State fisheries management agencies (DMR, IF&W, and MASC) as expressed in their December 2001 “Draft Fishery Management Plan for the Presumpscot River Drainage.” (see Section 5 and Appendix C of this report).It also does not address the US Fish and Wildlife Services goals, as reflected in their filings to FERC prescribing fish passage on the dams below the Eel Weir Dam, provided passage is achieved at the Cumberland Mills Dam, and sufficient numbers of migratory fish return to the river.
Option 3 – Smelt Hill Dam is removed and sea run
fisheries are restored
In addition to the removal of the Smelt Hill Dam, and potentially efforts to enhance resident fisheries in some areas, this Option involves active efforts to restore sea run fish.At present, three methods are used to restore access for sea run fish.These methods include:
§dam removal;
§providing fish passage at dams (fish ladders or fish lifts); and
§trap and truck efforts (trapping fish at a dam and transporting them upriver beyond dams without passage). However, this method is not considered by the responsible State and Federal agencies to be a viable long term option for restoring fish access on the Presumpscot.While trap and truck operations may have important short-term value (e.g., to get runs of sea run fish reestablished before permanent access is provided), in general this methods can result in high mortality rates, effectiveness can be limited – particularly for species which are very abundant, operating costs can be high, and they require active and reliable efforts, in some cases over long seasons.
A.What
would result from providing fish passage at up to 3 dams?
Description:In addition to the removal of the Smelt Hill dam, fisheries could be further restored by providing up and downstream fish passage for migratory species at up to three dams on the river.Most species will not be able to pass more than three dams in sufficient numbers to warrant passage beyond the third dam.The first three dams above Smelt Hill are the Cumberland Mills Dam, Saccarappa Dam, and Mallison Falls Dam.Fish passage is assumed to include fishways for upstream migrations of shad, blueback herring, and Atlantic salmon, a trap and truck facility at Saccarappa, a separate facility for upstream migration of eels, and downstream fishways serving all species except eels.Downstream eel passage would be provided by shutting down turbines at selected hours.
Costs:If passage was installed at the lowermost three dams- Cumberland Mills, Saccarappa, and Mallison Falls dams, it would likelycost 6 – 8 million dollars according to the US Fish and Wildlife Service (See also Appendix Table B-1).If fish did not ascend in sufficient numbers above the first dam to warrant passage at a second dam (if passage efficiency was75% or less) then the cost of this option would be approximately $1 million.These costs do not include power from diversion of flows to fish passage facilities or increased operating costs. Costs could be borne by industry, government, private donations, or some combination of these sources (industry may be the most likely source).
Effects
on Migratory Fish:Estimates
of the size of fish spawning runs resulting from installation of fish passage
at up to three dams are provided below. The size of the fish runs depends
on the success of the fishways in getting fish to spawning areas above
the dams, or the efficiency of the fish passage facilities in passing fish
over the dams into the upstream reaches.Not
all fish that attempt to negotiate a fish ladder or lift succeed.The
US Fish and Wildlife Service designs fishways assuming a 90% efficiency
rate (90% success rate).There are
few studies that document actual efficiency.However,
it is known that, for a variety of reasons, not all fishways are equally
effective, with some of the older fishways installed during the last twenty
years (when federal licenses began including requirements for fish passage)
having proved to be particularly ineffective.Learning
from these early efforts, the FWS has revised its fishway designs to improve
passage success.The Maine DMR’s “best
guess” on the range of possible efficiencies is 75% (worst case) to 90%
(design goal).The Maine DMR has computed
estimates of shad, alewife and blueback herring spawning runs on the
Under
the scenario assuming a 75% passage efficiency (the worst case scenario),
the DMR models indicate that fish passage would not be effective at more
than one dam; that is, it is expected that the run may not develop enough
to warrant passage to areas above a second dam .At
90% efficiency, it is estimated that fish could be passed in sufficient
numbers to warrant passage at three dams, at
The
size of the Atlantic salmon run resulting from access to habitat as far
as Little Falls dam is estimated below as a range reflecting two different
analyses: (1) Analysis based on MASC estimates and assumptions; and(2)
Estimates prepared by the Louis Berger Group for the Federal Energy Regulatory
Commission.Neither of the estimates
include the increased run that could develop through trap and truck operations
from Saccarappa Dam to sites above Little Falls.
Effects
on Resident Fish:Resident fisheries
would not change appreciably since habitat conditions would remain unchanged
above the Cumberland Mills dam.
Consistency
with State and Federal Management Goals:This
approach does not meet the goals and objectives of the State fisheries
management agencies (DMR, IF&W, and MASC) as expressed in their December
2001 “Draft Fishery Management Plan for the Presumpscot River Drainage.”
(see Section 5 and Appendix C of this report).It
also does not address the US Fish and Wildlife Services goals, as reflected
in their filings to FERC prescribing fish passage on all the dams below
the Eel Weir Dam, provided passage is achieved at the Cumberland Mills
Dam, and sufficient numbers of migratory fish return to the river.
Estimated
Migratory Fish Runs with Fish Passages Installed on Up to Three Dams
|
Migratory
Species
Runs
reaching Saccarappa dam with 75% passage efficiency and Little Falls dam
with 90% passage efficiency |
Up to Saccarappa DamUp
to Little Falls Dam |
|
|
American
shad(including
runs on the Piscataqua and the Little River) |
7,400 –
29,300 |
13,000 –56,5002 |
|
alewives(below
|
150,000
– 200,000
|
150,000
– 200,000
|
|
blueback
herring(including
a run on the Piscataqua and Little River)
|
96,8003
|
187,0003
|
|
Atlantic
salmon(access
up to Saccarappa Dam at 75% effic.; to Little Falls Dam at 90%)
|
23
– 1153(MASC)4;
NA
5 |
93
– 465 (MASC)4
Negligible
(Berger) 5 |
|
American
eel
|
increased
numbers
|
increased
numbers
|
|
striped
bass
|
unknown
numbers
|
unknown
numbers
|
|
1`Assumes
that at 75% efficiency,fish passage
is warranted at only one dam (Cumberland Mills); at 90% efficiency, it
assumes fish passages are warranted at Cumberland Mills dam, Saccarappa
Dam, and Mallison Falls Dam. 2Based
on figures used by the Maine DMR to estimate shad runs; from data collected
between 1983 and 2000 on the 3 Estimate
by Maine DMR based on estimates of 600 river herring/acre on the 4
Estimated usingthe Maine Atlantic
Salmon Commission (MASC) procedures; assumed habitat in tributaries only
(Piscataqua River and Mill Brook below Cumberland Mills at 75% efficiency;
including also the Little River and Colley Wright Brook at 90%); assumed
10% loss of smolts at each dam during downstream migration (5% at Cumberland
Mills); assumed 1 to 5% survival of smolts return as adults,. 5The
Berger Group, Inc. estimated salmon restoration potential for FERC (see
DEA, [FERC, 2001]).This analysis
did not estimate numbers of salmon for reaches of the river below Saccarappa
Dam; and concluded that there would be negligible salmon habitat available
with the dams in place and fish passage installed. |
||
B. What
would result from removing 3 dams and providing fish passage at up to 3
others?
Description:Removing
3 dams and providing fish passage at up to 3 others on the
Costs:Removal
of three dams on the lower river (Saccarappa, Mallison, and Little Falls)
could cost on the order of $3 million. Costs for fish passage at Cumberland
Mills, Gambo and Dundee, and downstream at N. Gorham are estimated to be
in the range of $6 to $10 million, depending on whether upstream passage
into the Dundee impoundment is provided through a fish lift or a trap and
truck facility.However, if fish did
not ascend in sufficient numbers above the first dam to warrant passage
at a second dam (if passage efficiency was75% or less) then the cost of
passage under this approach would be approximately $1 million. The total
cost of removals plus passage for this scenario would be on the order of
$4 million with 3 dams removed and passage at only one dam, and $9 million
to $13 million with 3 dams removed and the full program of fish passage
describedabove (see also Appendix
Table B-1). These costs do not include power lost due to dam removals and
to diversion of flows to fish passage facilities, or increased operating
costs.
Effects on Migratory Fish:This approach would restore riverine habitat in certain sections of the river where impoundments are eliminated by dam removal.This would increase the habitat suitability for species such as American shad and river herring, and would result in larger runs of sea run fish, because substantially more habitat (particularly above Gambo dam) would become available.The following table shows the approximates size of the spawning runs that these measures would be expected to restore, by providing access to spawning habitat in the river and its tributaries as far as the Dundee impoundment and, for Atlantic salmon, the North Gorham impoundment and Eel Weir Bypass.
Effects on
Resident Fish:Resident fisheries
would adjust to a 7.5 mile increase in the availability of free-flowing
riverine stretches as a result of dam removals.Combined
with the river restoration resulting from the removal of the Smelt Hill
dam, and the previously restored river at the Eel Weir Bypass, 16 miles
of the total 26 mile length of river would be restored, providing increased
habitat for trout and salmon.Habitat
area for bass and other resident species could decrease, though habitat
quality could improve as a result of improved conditions for macro invertebrates
and primary productivity from increased light penetration, and increased
forage base from restoration of migratory fishes (more eggs and juvenile
fishes).
Consistency
with State and Federal Management Goals:This
approach would meet the goals and objectives of the State fisheries management
agencies (DMR, IF&W, and MASC) as expressed in their December 2001
“Draft Fishery Management Plan for the Presumpscot River Drainage.” (see
Section 5 and Appendix C of this report); and would address the US Fish
and Wildlife Services goals, as reflected in their filings to FERC prescribing
fish passage on all the dams below the Eel Weir Dam, provided passage is
achieved at the Cumberland Mills Dam, and sufficient numbers of migratory
fish return to the river.
Estimated Migratory Fish Runs with Three Dams Removed
and Fish Passages Installed on Up to Three Dams
|
Migratory
Species
(Runs
reaching Gambo dam with 75% efficiency and N. Gorham dam with 90% efficiency;
Atlantic salmon reaching the Eel Weir Bypass with trap and truck) |
Runs
as far upRuns up to N.Gorham Dam
as Gambo DamAtlantic
salmon into Eel Weir Bypass |
|
|
American
shad(including
runs on the Piscataqua and the Little River at 75% and additionally the
|
15,700 –62,3002 |
34,500 –
136,5002 |
|
alewives(below
|
150,000
– 200,000
|
150,000
– 200,000
|
|
blueback
herring(same
distribution as American shad)
|
205,9003
|
450,2003
|
|
Atlantic
salmon
|
102 - 508 (MASC)4;
34 - 102 (Berger)5 |
206 – 1,030 (MASC)4
34 - 102 (Berger)5 |
|
American
eel
|
increased
numbers
|
increased
numbers
|
|
stripedbass
|
unknown
numbers
|
unknown
numbers
|
|
1`Assumes
that at 75% efficiency, fish passage is installed at only one dam (Cumberland
Mills) and Saccarappa, Mallison Falls, and Little Falls dams are removed,
making habitat accessible up to the Gambo dam; at 90% efficiency, it assumes
fish passage is installed at Cumberland Mills dam,Gambo
Dam, and Dundee Dam;and Saccarappa
Dam, Mallison Falls Dam, andLittle
Falls dam are removed. 2Based
on figures used by the Maine DMR to estimate shad runs; from data collected
between 1983 and 2000 on the 3 Estimate
by Maine DMR based on estimates of 600 river herring/acre on the 4
Estimated using the Maine Atlantic Salmon Commission (MASC) procedures;
assumed habitat in tributaries only (not the mainstem), including (below
Cumberland Mills) the Piscataqua River and Mill Brook, and (above Cumberland
Mills), Little River, Colley-Wright Brook (for 75% scenario) plus Pleasant
River, and Eel Weir Bypass for 90% scenario. Assumed10%
loss at each dam during downstream migration (5% at 5The
Berger Group, Inc. estimated salmon restoration potential for FERC (see
DEA, [FERC, 2001]) if the Saccarappa Dam, Mallison Falls Dam, and Little
Falls Dam were removed and passage were provided at the Cumberland Mills
dam (but not at the Gambo dam above Little Falls).This
analysis did not estimate numbers of salmon for reaches of the river below
Saccarappa Dam; assumed a return rate of 0.5% - 1.5%; assumed 1.76 miles
of the mainstem would become suitable habitat, and 25% (10 miles) ofthe
Little River, but not Colley-Wright Brook (which MASC considers habitat). |
||